PONTYPOOL GLYN PITS
Updates
Both engine houses have had work done to re-bed the masonry on the tops of both buildings. Further work has been undertaken on the vertical winder house in the form of angle corner pieces, and tie-rods at a high level on all corners. The scaffolding on the pump house will be left in position, to act as shoring for the outer walls. Builders 'Acrows' & hard-wood supports have been used on both buildings to support lintels and window arches.
![]() | ![]() | ![]() |
---|---|---|
![]() | ![]() | ![]() |
![]() | ![]() | ![]() |
​
Both the Vertical Winder House and the Beam Engine House have now had galvanised roofs fitted along with breathable mesh at the windows in order for the building to have a chance to dry out.